Contractors, GTB Demolition have completely flattened all three Southport Community fire station buildings, dug up most of the concrete foundations and sorted out the scrap iron into piles. The large chuncks of concrete will be broken down into small pieces and used as crusher run.

Work on the new fire station will start later this month.